In a report on major UK Ministry of Defence (MoD) projects published by the National Audit Office (NAO) on November 16, final costs for cancelling the much-troubled Nimrod MRA4 programme were finally confirmed.
The original contract for 21 Nimrod Maritime Reconnaissance and Attack Mk4 aircraft was placed with BAE Systems in 1996 at a cost of £2.8 billion, with a projected in-service date of April 2003.
But the report says that “Programme difficulties stemmed from ‘the design challenge being hugely underestimated by industry’
compounded by a weak programme management culture,
which lacked transparency, neglected or overrode project control systems and disciplines,
and produced forecasts that ‘lacked depth and reality’.”
Several renegotiations of the contract during the period 2002 to 2008 resulted in the procurement number of aircraft dropping to first 18, then 12 and finally just nine.
Meanwhile delays, caused by “Departmental funding constraints, leading to resources being re-prioritised in the short term; and industry underestimating the design challenge and technical complexity in their initial forecast schedule,” according to the report, meant the in-service date slipped by 114 months, very nearly ten years.
The projected cost had risen to £3.4 billion, equating to £378 million per aircraft.
The NAO reports notes that “The MoD reported that each reduction in aircraft numbers still allowed the defence requirement to be met, but only after adjusting down the requirement on each occasion, as the reductions were financially driven.”
Options to cancelling the project were considered before October 2010, notes the report. These included completing production of all nine aircraft, or just the three that were largely complete.
Completed aircraft could be kept for future sale or storage.
But the MoD “judged continuing production as risky, because it could involve further difficulties and cost increases of the type that had already been encountered on the project to date.
” Keeping the workforce employed at the Woodford plant was also an issue, as BAE Systems had already indicated the site would be closed on completion of the Nimrod contract.
Storing any finished aircraft was also discounted on the basis that it would be “too expensive to recover the aircraft, such as upgrading and re-establishing training facilities.
It could take two to three years from the date of any decision to do so.”
By cancellation in October 2010, the report states that “95% of forecast spend for completing the nine aircraft had been used, leaving around £200 million to spend” from the £3.4 billion project.
Most of this money was used to scrap the aircraft, but the report acknowledges that there are “some termination costs” currently under negotiation with BAE Systems and therefore cannot yet be published.
Although the NAO is concerned primarily about cost, it has also considered the capability gap left by cancellation of Nimrod.
It states “The MoD has assessed that the Nimrod maritime patrol aircraft contributed to eight of the 15 security priority risks described in the National Security Strategy -
Nimrod was uniquely able to rapidly search large maritime areas, a capability relevant to long-range search and rescue, maritime counter terrorism, gathering strategic intelligence, and protecting the nuclear deterrent.
“Some limited analysis was carried out on how specific military tasks could be covered by a combination of Sentry surveillance aircraft, Hercules transport aircraft and the Merlin maritime helicopters.
However, the MoD noted that there would be ‘significant shortfalls without significant investment, and the co-ordination of such assets at the right place and the right time might prove to be very risky’.
Using other existing assets would provide a reduced capability compared with Nimrod, and diverting resources from existing tasks would have wider implications for defence.
The Sentry surveillance aircraft is already at minimum crew and aircraft numbers to cover NATO commitments.
Using helicopters, such as the Merlin or Lynx, would affect national commitments or training of crews for other tasks. Other alternatives are fully committed to current operations.”
In response to the NAO report, the Secretary of State for Defence, Philip Hammond, said: “It was right to take tough decisions in the Strategic Defence and Security Review to deal with an equipment programme that was out of control.
The Nimrod MRA4 was over eight years late, almost £800 million over budget, and had seen the unit cost of each aircraft soar by 200%; with no clear idea of when the capability would be delivered.”
Nimrod MRA4 cancellation: the final costs now confirmed...
Forum rules
- Stratofreighter
- Scramble Master
- Posts: 22220
- Joined: 25 Jan 2006, 08:02
- Location: Netherlands
Nimrod MRA4 cancellation: the final costs now confirmed...
http://www.key.aero/view_news.asp?ID=44 ... n=military
December 2024 updates at FokkerNews.nl....
- Le Addeur noir
- Scramble Master
- Posts: 65420
- Joined: 19 Jan 2007, 16:22
- Subscriber Scramble: Nee
- Location: Asie
Re: Nimrod MRA4 cancellation: the final costs now confirmed...
There should be people shot over this.
The money wasted could have been used to purchase the Boeing P-8.
The Nimrod MRA.4 project was doomed from the start and expert opinion stated this in the mid-nineties,but was not heeded by the UK MoD.
Corruption and incompetence,the hallmarks of the UK Ministry of Defence.
The money wasted could have been used to purchase the Boeing P-8.
The Nimrod MRA.4 project was doomed from the start and expert opinion stated this in the mid-nineties,but was not heeded by the UK MoD.
Corruption and incompetence,the hallmarks of the UK Ministry of Defence.
Drink treble
See double
Act single
and the Emir called up his jet fighters
See double
Act single
and the Emir called up his jet fighters
- The Crunchy Nutter
- Posts: 7
- Joined: 23 Nov 2011, 09:40
- Type of spotter: F2
- Subscriber Scramble: No
- Location: EGBB / BHX
- Contact:
Re: Nimrod MRA4 cancellation: the final costs now confirmed...
More like the hallmarks of the UK GovernmentLe Addeur noir wrote:Corruption and incompetence,the hallmarks of the UK Ministry of Defence
Re: Nimrod MRA4 cancellation: the final costs now confirmed...
I'm still in awe how the aviation industry gets away with this whereas in any other industry, a fixed price contract is a fixed price contract - with sufficient penalty clauses to make non-delivery an extremely expensive option for any supplier. It's not just the MR4 - just look at the F-35! Everytime someone sneezes or a bird outside my window sh*ts, the plane gets more expensive!
- Polecat
- Scramble Master
- Posts: 5048
- Joined: 12 Jul 2007, 13:58
- Type of spotter: Omnivore
- Subscriber Scramble: Polecat
- Location: The Middle East of The Netherlands
Re: Nimrod MRA4 cancellation: the final costs now confirmed...
..dreamliner, A400M, A380, even loads of bizjets don't make their projected first flight and /or in service dates...Erik_7Xi wrote:I'm still in awe how the aviation industry gets away with this whereas in any other industry, a fixed price contract is a fixed price contract - with sufficient penalty clauses to make non-delivery an extremely expensive option for any supplier. It's not just the MR4 - just look at the F-35! Everytime someone sneezes or a bird outside my window sh*ts, the plane gets more expensive!
But it's not just with aviation industries if u ask me; the building/contracting industry (Station Arnhem, Rijksmuseum, NZ-lijn), IT, or health care also habve their "íssues" ....
But with the Nimrod it was felt that it was already superior to P-3/ATL, so an improvement would make it even better... I think saving British defence jobs, as well as wanting a superb "White Elephant" may have been the main consideration when the programme was given a go-ahead...
Last edited by Polecat on 24 Nov 2011, 16:27, edited 1 time in total.
I have never drunk milk, and I never will . . . .
- Richard from Rotterdam
- Scramble Master
- Posts: 2680
- Joined: 09 Aug 2004, 12:38
Re: Nimrod MRA4 cancellation: the final costs now confirmed...
Yep, as long as it came with a mobile fire extinguisher the Nimrod was superb!
Let's face it: governments are still in awe by the sexiness of the aerospace industry and are therefore always willing to pay shedloads of money towards epic failures. Over half of the military jet developments worldwide can be included, and most probably in the near future we can include Fokker. Again.
Let's face it: governments are still in awe by the sexiness of the aerospace industry and are therefore always willing to pay shedloads of money towards epic failures. Over half of the military jet developments worldwide can be included, and most probably in the near future we can include Fokker. Again.